The Redfish Extension will have 209 new homes: 116 Junior Enlisted three and four bedrooms and 93 Company Grade three and four bedrooms.
The first portion of Phase I will be Junior Enlisted homes and are expected to be completed at the end of February 2008. Priority for the new homes will be:
- Tenants relocated for demolition of their existing home.
- Tenants on wait list.
Once the first two priorities are exhausted, relocation availability and policy information will be provided to the current residents. There will be stipulations for current residents that will include: lease obligation fulfillment, time remaining at Tyndall, unit condition pre-inspection and discrepancy and complaint history.
Other than Sentry Lane, the demolition schedule for Wood Manor has not been determined at this time.
New construction information including timelines for Field and Senior Grade Officer homes will be provided in Spring 2008.